Dear All,
In Navision 5.0
In Planning Worksheet, BOM components of the parent material not shown when running Functions - Calc Regenerative Plan.
Set up created
1. Created BOM & Routing for the Parent Material.
2. Attached BOM & Routing to the Parent Material Item Card.
3. Replenishment system - Prod. Order, Manufacturing Policy - Made-To-Stock & Reordering Policy - Order.
Kindly help me in this matter.
Thanks & Regards
Santosh
Where Stones can be transformed to Gold
0
Comments
Is there any demand?
Are you using SKU's?
What is the components at location setting?
What are the components of the BOM's planning settings?
.....................................
I have used the same configuration in Nav 4.0, & its working fine!!!
So could anyone advice on this to me.
Santosh
Where Stones can be transformed to Gold
Could you suggest what we can do on it?
Santosh
Where Stones can be transformed to Gold
[Inappropriate/Offensive text removed by Moderator.]
U JUST DESERVED THAT.
Santosh
Where Stones can be transformed to Gold
Can anyone advice?
Cos the same configuration works in Nav 4.0, but not in Nav 5.0.
Santosh
Where Stones can be transformed to Gold
Mine works in 4 and 5 without hotfixes, so it is not an issue.
The issue here is you are asking for us to solve your problem without actually giving us the symptoms of your problem. My simple answer is you "think" the setup you have in 5 is the same as 4, but actually it is not, you have made an error.
Run Cronus in 5 - does it work for you?
Kindly advice me on where I have missed the setup.
While running Calc Regenerative Plan for Component & RM, the lines are not created in Planning Worksheet.
Created FG, WIP & RM.
For FG ITEM, Replenishment system - Prod. Order
For WIP ITEM, Replenishment system - Prod. Order
For RM ITEM, Replenishment system - Purchase
For FG ITEM, Manufacturing Policy - Make-to-Stock
For WIP ITEM, Manufacturing Policy - Make-to-Stock
For RM ITEM, Manufacturing Policy - Make-to-Stock
For FG ITEM, Reordering Policy - Order
For WIP ITEM, Reordering Policy - Order
For RM ITEM, Reordering Policy - Fixed Order Qty
For FG ITEM, Flushing Method - Manual
For WIP ITEM, Flushing Method - Manual
For RM ITEM, Flushing Method - Manual
For FG ITEM & For WIP ITEM - Routing & BOM linked ( ROUTING & BOM CERTIFIED ).
Machine Center in routing for FG & WIP ITEM has Calendar calculated.
Forecast of the FG ITEM in Production Forecast is within the Order date & Ending Date while runnig Calc Regenerative Plan. Also marked MPS & MRP checkbox
Thanks in Advance.
Regards,
Santosh
Santosh
Where Stones can be transformed to Gold
A value entry ( Eg. 1 ) was given in Forecast for Components & RM.
Then run MPS for Finished Goods in Planning Worksheet using Calc Regenerative Plan.
Then run MPS & MRP for Components & RM using Calc Regenerative Plan.
This time plan for the components is displayed in Worksheet.
When the value entry is not given, components cannot be planned. But I think I still miss the setup somewhere. Finding it out...
Santosh