Multilevel Production BOM/RPO - Make to Order Scenario.

vsalotvsalot Member Posts: 47
We are using Multilevel, say 10 levels, of BOM/RPO for one Production/Finish Item with Make-to Order Scenario.

We needs to replan/Reschedule the existing RPO once partial Output was getting posted for 2-3 levels of semifinish Goods.

Can we have such facility or an alternate solution in Dynamics Nav.??

Comments

  • kapil4dynamicskapil4dynamics Member Posts: 591
    Try changing starting date and ending date at RPO lines and then running get action messages on planning worksheet.
    Kapil Khanna