From the planning worksheet you can create a PO as planned, firm planned, etc.
Are there any problems modifying this option with the "released" option. My customer now has to create the PO's first as firm planned. (1300 PO's take 1 hour to create) After this he changes the status to "released" (again 1 hour)
Seems to be a step they want to skip. Any hints or is this easy?
0
Comments
NAV Freelance Consultant
Why you want to change status after you create? Released means you've started to produce. Usually you have firm planned for few days.
That form takes 1 hour to create 1000 PO's. I want to skip that form.