When we run MPS & MRP in the planning worksheet, the field 'Refence order type' is getting defaulted to 'Planned'. May i know where from this is getting flown. Is there any setup available. I wish to direct it to 'Firm planned'. where should i go and define this ?

Regards,
Venkatesh
Thanks and Regards,
Venkatesh

Comments

  • kapil4dynamicskapil4dynamics Member Posts: 591
    I think while running the planing worksheet for Sales u have selected Planed orders while doing carry out action msg.

    Select firm planned there then in ur MRP run it will be firm planned. :)