Hi,
I need help in following issue.
PO Qty released 100 Nos
Qty receive 100 Nos
Qty rejected 10 Nos
Qty Accepted 90 Nos
In Navision it get's closed or can not be used further inspite of there is balance of 10 Nos due to rejection. Here many times the qty rej.is very less and for which we can not raise new PO because of work flow system to follow which again through various Authorities.
Is there any alternative that we can use the same PO for balance qty to be received ?
Thanx
Prashant
0
Comments
(I assume you are not using any QC module)
if using any QC module there should be provision for "QC before receipt". this allows you to receive only the approved qty. and the rejected qty. does not bother you at all.
if possible there could be slight change in the bussiness process. you post receipt only once the quality is done so that you can post the actual qty recd. and po still open to receive remaining.
Ritesh K Singh
If you are doing modifications then be sure of what you are doing.