Planned Production Order

ramyavenkatramyavenkat Member Posts: 94
Manufacturing queries


1. while creating a planned production order, the due date field in the header is mandatory. what is the process of forward scheduling the job,with a starting date and no end date?

2. Also when scheduling,the system auto calculates the dates taking into account 100% of the machine load . is there any way by which we can have a distributed load over a time period?

3. how can i distinguish similar machines with different efficiencies, within a machine center with the same routing operation?

REGARDS

Ramya Venkat

Comments

  • santoshmkcetsantoshmkcet Member Posts: 229
    1. while creating a planned production order, the due date field in the header is mandatory. what is the process of forward scheduling the job,with a starting date and no end date?

    Here you have to manually enter the due date. The starting date will change according to the due date entered....
    Thanks & Regards
    Santosh