Dear Nav Users,
Can some one help me to on the following scenario in Navision 4.0 SP1, 5.0..
System LCY : USD
Routing lines has few operations of which one of the operation is a sub-con operation for which the unit cost is defined as 1 USD (Example) per unit. (In the routing lines the unit cost needs to be defined in LCY)
The subcon vendor currency is SGD and the exchange rate set is 1.5 (1 USD = 1.5 SGD)
While running the sub-con worksheet --> Calculate subcontract system has suggested the purchase order with unit cost as 1.66 SGD. This cost fluctuates based on the exchange rate. But in actuals i have a contract with my vendor for a fixed price of 1.7 SGD per piece which i m unable to maintain in the routing lines as the unit cost needs to be defined in LCY.
Because of the above scenario, every time i need to go and amend my purchase order manually for the cost with respect to currencies other than LCY.
Regards,
Venkatesh
Thanks and Regards,
Venkatesh
0
Comments
Venkatesh