Hi ,
I have Three Shifts in production which time is:
Shift-A 6:00:00 AM to 1:59:59 PM
Shift-B 2:00:00 PM to 9:59:59 PM
Shift-C 10:00:00 PM to 5:59:59 AM
When I am Work days for Shift-C Error Derive Below.
Ending time must be higher then starting time.
How Can I create shift-c time workdays .
plz...any help.
Regards
Jasbir Singh
0
Comments
Maybe you can divide the last shift into two shifts
like: Monday 22:00:00-23:59:59 shift c
Tuesday 00:00:00-05:59:59 shiftc