After I run the planning worksheet there are no items come with results even they have the demand withing the given dates for the worksheet. Are there any parameters that we need to set up for the items. I got the white paper but it described only how it works. I have tested some items by setting their Reordering policy to Order. But it won't work.
Any help on this
0
Comments
Using Components at Location in Manufacturing Setup?
Using Stockkeeping Units?
All these things have an effect on the way the planning system behaves.
www.NextEqualZero.com
A technical eye on Dynamics NAV
Use Fixed Reorder and define a reorder point as well, much easier.
However, I would guess your components at location is blank and you are not using SKU's, put "anything" in the components at location and see what happens.
No other specific filters used to run the sheet. Only give the related items, and the location that we need to run the planning and give only the order date and the ending date.