starting date and the ending date

reemareema Member Posts: 255
Hi experts,
When I run the Planning worksheet for the production order system is generating starting date and the ending date .

Please let me know how it is caluclating the starting date and the ending date ?

please........

thanks and regards
reema

Comments

  • santoshmkcetsantoshmkcet Member Posts: 229
    reema,

    u seem to have lot of questions in ur mind,

    do u have a manufacturing manual with u?

    well coming bak to the q?, starting & ending dates are calculated based on

    1. due date on the po
    2. set up time , run time, all other times set in routing
    3. & also the time u have set for the machine, whether the m/c runs from 8am to 4pm, or from 12.00.00 am to 11.59.59 pm etc.

    u got it?

    santosh
    Thanks & Regards
    Santosh