How can one adjust a wrong consumption entry for a finished prod. order in NAV 4.0, and if possible does it also affect the actual cost of that finished prod. order?
Sandeep Saleem
ATNA Technologies India Pvt Ltd
Bangalore
India

Answers

  • vanrofivanrofi Member Posts: 272
    In what way it was wrong?
    wrong quantity?

    I'm afraid it is not possible. I was thinking about a revaluation journal, but that's only for positive entries.

    You could change the cost of the output to start with and change that to what it really needed to be?

    To much or to little consumption can be rectified with item journal?
  • sandeepsaleemsandeepsaleem Member Posts: 11
    Thnaks pal, just needed to confirm.