I must be missing an essential step somewhere. I am trying to work out how to do the typical process of
offer -> offer accepted -> create job -> import details of offer into job predicted costs
All the training materials start with a job and then add job planning lines. Starting with a job doesn't make any sense and it also doesn't seem to be possible to generate an offer from project lines.
Anyone done this before?
Ian
0
Comments
I'm right now in the process of creating a function that creates job task and planning lines based on the sales quote.
I've defined extra fields on the sales line which I use for grouping sales line to 1 job task line.
Tino Ruijs
Microsoft Dynamics NAV specialist
I could understand if it was the other way around and functionality to convert a quote to task lines was not present - but who creates a project and then quotes for it? Everyone does the opposite.
Let me know if your module is near completion - it may be of interest.
Thanks
Ian