MS Project 98 & NF

fritsk256fritsk256 Member Posts: 5
edited 2000-10-03 in Navision Financials
Hello everyone, I've got the following problem:

How can I switch from base calendar Standard to Night Shift/24 Hours base calendar?
I've only got a button on a form and I just want to change the base calendar from Standard to Night Shift.


In MS Project 98 you can find it bij doing the following instructions: Resource Information -> Working Time tab -> base calendar -> Standard/Night Shift/24 Hours

With kind regards, Maikel Jeurissen