Our client wants to see actual (adjusted) item costs on job ledger entries. As standard, job ledger entries hold the cost picked up from the item at the time of entry. I am reluctant to tamper with the 'Adjust Cost - Item Entries' job, so I am imagining a separate batch job which picks up the cost-adjusted item ledger entry(ies) per job ledger entry and updates the 'Unit Cost' and 'Total Cost' on the job ledger entry.

However, it doesnt look as if there is enough information in the standard system to definitely identify which item ledger entry(ies) relate to any given job ledger entry. The client uses lot numbering, although I dont think this is relevant.

Does anyone have any suggestions about how I could approach this please.

Thanks in anticipation.

Bob

Comments

  • nunomaianunomaia Member Posts: 1,153
    Nuno Maia

    Freelance Dynamics AX
    Blog : http://axnmaia.wordpress.com/
  • bob_upbob_up Member Posts: 155
    Thank you. I have replied in that forum.
  • raj2000beraj2000be Member Posts: 36
    If you are using 5.0, there is a batch job already called "Update Job Item Cost". This does excatly when you have in your note.

    Regards
    Raj
  • bob_upbob_up Member Posts: 155
    Brilliant. I will look in V5 tomorrow to see what it does.
  • nunomaianunomaia Member Posts: 1,153
    raj2000be wrote:
    If you are using 5.0, there is a batch job already called "Update Job Item Cost". This does excatly when you have in your note.

    Regards
    Raj

    In NAV 5.0 job ledger entry posting was adapted match to item ledger entry. In version 4.0 that didn’t happened. Adjusting job entries in version 4.0 must be taken a different match.