Has anyone ever run across an easy way to create a production order that is processing costs only? I have a situation where the raw material and finished good are the same item. The production process only adds costs to the unit cost of the item. I was able to make it work by creating a component line equal to the item I was creating. That way the output and consumption were the same quantities and the work center assigned to the output added overhead, processing costs etc. Is this the best way to handle this?