Reprocessing is that where, if after a particular process during quality inspection.some quantity was rejected .Then that quantity again processed with some changes in the process e.g varying the temprature ,or adding certain chemicals
Reprocessing is that where, if after a particular process during quality inspection.some quantity was rejected .Then that quantity again processed with some changes in the process e.g varying the temprature ,or adding certain chemicals
As long as the production order is not finished you can always post additional consumption and output throughout all the operations (also negative consumption and output if that is required).
It is quite common to have a QC inspection being the last operation in the routing, this way it is the QC results that determines the quantity of the finished product that goes into inventory and if some or all units needs to be reworked you just post additional consumption and output on those prior operations and then finish the order once all is approved.
Comments
What do you mean by "reprocess"? Are you trying to reverse the output and consumption?
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
I am doing production reprocess adding items in components but is there any provision to it will not count/add as production.
Because in production report it has been shown which i have already produced .
Instead of using reject use rework functionality of B2B Quality module. \:D/
As long as the production order is not finished you can always post additional consumption and output throughout all the operations (also negative consumption and output if that is required).
It is quite common to have a QC inspection being the last operation in the routing, this way it is the QC results that determines the quantity of the finished product that goes into inventory and if some or all units needs to be reworked you just post additional consumption and output on those prior operations and then finish the order once all is approved.
My Dynamics NAV Blog: olofsimren.com
My Google Plus Profile
Naviona - My Dynamics NAV Partner
I am doing production reprocess adding items in components but is there any provision to it will not count/add as production.
Because in production report it has been shown which i have already produced .