Hello
Has anybody done a data migration with where Customer has production order outstanding and WIP.
What is the proper way to load these production orders?
Hello
Has anybody done a data migration with where Customer has production order outstanding and WIP.
What is the proper way to load these production orders?
Thank you.
Consider this idea,
1. Load all opening production orders.
2. Set all material to not include inventory in planing tab.
3. Run requisition to calculate all materials for these production orders, direct them to one fake vendor, reveive all materials.
4. Issue all materials to those opening production order.
5. Reverse GL impact on that vendor's AP.
talked the client to make the gl transactions when the production orders are done.
tnx
This is very dangerous. The main concern here is that your inventory valuation will not be able to match G/L once the client makes g/l postings into your inventory g/l account.
Well in more detail the finished good will be positive adjusted into inventory. The Gen bus. Posting Group will changed so that adjustment account will be WIP.
So in sense
Comments
Consider this idea,
1. Load all opening production orders.
2. Set all material to not include inventory in planing tab.
3. Run requisition to calculate all materials for these production orders, direct them to one fake vendor, reveive all materials.
4. Issue all materials to those opening production order.
5. Reverse GL impact on that vendor's AP.
tnx
This is very dangerous. The main concern here is that your inventory valuation will not be able to match G/L once the client makes g/l postings into your inventory g/l account.
AP Commerce, Inc. = where I work
Getting Started with Dynamics NAV 2013 Application Development = my book
Implementing Microsoft Dynamics NAV - 3rd Edition = my 2nd book
So in sense
Debit Finished Good Inventory
Credit WIP.