Adjustment factor - change of standard cost in item card

kiyackiyac Member Posts: 118
Version : 4.0
Costing method : Standard Cost
Existing Standard Cost = 0
With item ledger entries

Now I want to change the item card's standard cost from 0 to 3,
Both adjust item cost/price or standard cost worksheet can be used for changing item card's standard cost for the item which already has item ledger entries.

Question come, what should be input in the adjustment factor field for this case (from 0 to 3)? #-o
As I know the formula is,
New standard cost = Old standard cost * adjustment factor

Thanks for your reply

Comments

  • kiyackiyac Member Posts: 118
    I get the solution.

    For this case (standard cost change from 0 to something).

    In standard cost worksheet, do not use funciton >"suggest item standard cost" (which only provide "adjustment factor" solution).
    Just directly input the new standard cost in "New standard cost" column in standard cost worksheet.

    :mrgreen: