Hello,
My client has three shifts in his factory.I have declared all the three shifts in the workshop calendar,but I am not able to get the effect of all the three shifts.The production schedule & Capacity Gantt chart show only one shift in working.
Please explain my mistake.
Shreenivas Vaidya
0
Comments
I have already tried by calculating calendars for work center and machine center.It did not work.