Hi,
I noticed that if I have a PO line which is partially received, while running the MRP Navision ignores this line also. Ex., Raw material Item A requirement is 1000 / PO line – 250 / Received – 50 / Outstanding to receive – 200/
Qty suggested while running MRP is = 1000 – 50 = 950 / System is not considering the outstanding Qty to receive ie., 200
Is that any set up I am missing ? Any solution for this ?
Thanks and Regards,
Venkatesh
0
Comments
I believe this was a known bug in early versions of 4 (?) I suggest you put this back to your reseller, or check with Microsoft. I am 90% sure a hotfix was issued for this.