Discussions
Activity
Best Of...
Sign In
·
Register
Home
›
Navision Attain
Howdy, Stranger!
It looks like you're new here. Sign in or register to get started.
Sign In
Register
Quick Links
Categories
Recent Discussions
Activity
Best Of...
Unanswered
Categories
All Categories
73
General
73
Announcements
66.6K
Microsoft Dynamics NAV
18.7K
NAV Three Tier
38.4K
NAV/Navision Classic Client
3.6K
Navision Attain
2.4K
Navision Financials
115
Navision DOS
854
Navision e-Commerce
1K
NAV Tips & Tricks
772
NAV Dutch speaking only
615
NAV Courses, Exams & Certification
2K
Microsoft Dynamics-Other
1.5K
Dynamics AX
310
Dynamics CRM
109
Dynamics GP
10
Dynamics SL
1.5K
Other
993
SQL General
384
SQL Performance
34
SQL Tips & Tricks
34
Design Patterns (General & Best Practices)
Architectural Patterns
10
Design Patterns
5
Implementation Patterns
53
3rd Party Products, Services & Events
1.7K
General
1.1K
General Chat
1.6K
Website
79
Testing
1.2K
Download section
23
How Tos section
260
Feedback
12
NAV TechDays 2013 Sessions
13
NAV TechDays 2012 Sessions
MRP Order date and End date
s_venkatesh78
Member
Posts:
97
2007-09-11
edited 2007-09-13
in
Navision Attain
Hi
Anybody can explain me what is the Meaning and Relation between the 'Order date' and 'End date' that we enter during the MPS / MRP run ? Version 4.0
Thanks and Regards,
Venkatesh
0
Comments
AdamRoue
Member
Posts:
1,283
2007-09-11
The order date is the date to be used when creating suggested planned orders.
The ending date is how far forward to let the run look for demand. If you enter 31/12/2007 and sales orders in 2008 will not be considered.
The art of teaching is clarity and the art of learning is to listen
0
s_venkatesh78
Member
Posts:
97
2007-09-13
Hi,
Now i am clear with the End date. The example is very clear.
But still the Order date field is bit confusing. Can you help me to explain with an example.
Thanks and Regards,
Venkatesh
0
Sign In
or
Register
to comment.
Comments
The ending date is how far forward to let the run look for demand. If you enter 31/12/2007 and sales orders in 2008 will not be considered.
Now i am clear with the End date. The example is very clear.
But still the Order date field is bit confusing. Can you help me to explain with an example.
Venkatesh