Anybody can explain me what is the Meaning and Relation between the 'Order date' and 'End date' that we enter during the MPS / MRP run ? Version 4.0
Anybody can explain me what is the Meaning and Relation between the 'Order date' and 'End date' that we enter during the MPS / MRP run ? Version 4.0
Thanks and Regards,
Venkatesh
Venkatesh
0
Comments
-
The order date is the date to be used when creating suggested planned orders.
The ending date is how far forward to let the run look for demand. If you enter 31/12/2007 and sales orders in 2008 will not be considered.The art of teaching is clarity and the art of learning is to listen0 -
Hi,
Now i am clear with the End date. The example is very clear.
But still the Order date field is bit confusing. Can you help me to explain with an example.Thanks and Regards,
Venkatesh0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions