Remaining Qty is too Low in Item Ledger Entry

DemetreDemetre Member Posts: 19
Good Day to all.

I'm having a serious problem regarding Purchase Credit Memo applying.

I have an item in a Posted Purchase Invoice with quantity 12pcs.

That purchase invoice was wrong.(wrong costs)

In the meantime a SALE of 3 pcs took place and the remaining open item ledger entries of that item are 9pcs.

Then i created a Purchase Credit Memo of 12pcs and i tried to Apply (Appl.-to Item Entry field) this entry to the Posted Purchase Invoice.

The error is "Remaining Quantity is too Low in Item Ledger Entry no. = ‘.......’"

Is it possible to Unapply those 3 pcs from the sales invoice in order to "FREE" them so i could apply them to my Purchase Cr. Memo ?

Thnx in advance.
Demetris.

Answers

  • kinekine Member Posts: 12,562
    1) There is some customization which prevents you to have negative inventory
    2) You can do positive adj. of 3 PCS, post the Cr.Memo, do correct Invoice, do negative adj. but you must be sure that costs etc. will be correct (and all accounts etc.).
    Kamil Sacek
    MVP - Dynamics NAV
    My BLOG
    NAVERTICA a.s.
  • DemetreDemetre Member Posts: 19
    Thnx for the Reply.

    1. It has nothing to do with negative inventory.

    2. When i will do positive adjust for those 3cps a new Item ledger entry will be created.
    In orer to fix the cost i HAVE to apply my cr. memo with the wrong invoice.
    That means that i have to apply my purch.cr.memo with that specific item ledger entry of 12pcs and not with any other item ledger entry of any 3 or more pcs.
    Another problem is that u can not apply more than one item ledger entries in one Purchase Credit memo line.(i.e. apply for 12pcs -> 9 & 3)

    Hope that i was helpful.

    Please dont hesitate to give me any solutions, because i'm stuck.
    Thnx very much.
  • David_SingletonDavid_Singleton Member Posts: 5,479
    Well I know its too late to help in your case, BUT the good news is that in Dynamics NAV version 5.0 you can "un-apply Item ledger entries" and thus fix up costing issues like this.

    Actually the inventory costing in 5.0 is great, lots of little "Hmm but Navision should do this standard", it now "does standard".

    I guess you can't wait 6 months though.
    David Singleton
  • ssinglassingla Member Posts: 2,973
    As far as I have understod you are posting credit memo to reduce the cost of the purchase. There is an option on the purchase and payable setup "Return Shipment on Credit Memo", If this option is marked true then system post an return shipment entry therefore the system is giving an error "Remaining Qty low". In this situation you can use item charge in the purchase credit memo and do the item charge assignment on the posted receipt. There is secon option that the field "Return Shipment on Credit memo" should be marked false and use return order option whenever goods have to be shipped back to vendor.
    CA Sandeep Singla
    http://ssdynamics.co.in
  • DemetreDemetre Member Posts: 19
    Thanx to everybody.

    The solution came by taking ideas from all of you.

    1. Create a transfer (or positive adjustment) in the location where the remaining qty should be 12 (it was 9 + transfer 3 = 12) with the wrong cost.
    2. Create a credit memo with the same posting date as the wrong purchase invoice.
    3. create 2 lines in the credit memo, one with 9 pcs and one with 3 pcs.
    4. Apply the first line on the item ledger entry of the posted purchse invoice (9 pcs) an the second to the item ledger entry of the transfer (3 pcs)
    5 Apply the header of the Cr. Memo to the Header of the Invoice
    6. Post the Purchase Cr. Memo (Attention to the posting date)
    7. Run Adjust Cost Item entries at the date of the Posted Purchase Invoice.
    8. Create the opposite entry for your Transfer (or adjustment) but this time with the corrected cost and the todays date.

    Hope in version 5 with Unapply item ledger entries to avoid doing all the above.

    Thnx again.
    Demetre
  • ssinglassingla Member Posts: 2,973
    Not very convinced with the need of the entries/steps mentioned by you. If you have to decrease the cost of the purchase by issue of credit memo , you should select Charge Item option and assign it to the posted receipts.
    CA Sandeep Singla
    http://ssdynamics.co.in
  • ssinglassingla Member Posts: 2,973
    Posting "postive adjustement"/Transfer/"Negative Adjustement" entries without any actual transactions taking place is not the correct procedure.
    CA Sandeep Singla
    http://ssdynamics.co.in
  • ecclecticecclectic Member Posts: 176
    ssingla wrote:
    Not very convinced with the need of the entries/steps mentioned by you. If you have to decrease the cost of the purchase by issue of credit memo , you should select Charge Item option and assign it to the posted receipts.

    brilliant. never thought of that lol