problem with production order schedule time defining

nrapendra
nrapendra Member Posts: 208
hi all,

there is a simple prob.

in chemical industry there is a reacter which is set for process time
72 hrs.either we want to make 100 kg of chemical or 1000 kg.
it will take 72 hrs fixed.

the problem is that i have defined the runtime in route for 72 hrs.
for one kg.but when we go for the 100 kg it calculate the ending time in prod order 100*72 hrs.we can not change the unit bcaz if it will process 1 kg then it will run 72 hrs and if it will process 1000 kg then it will run 72 hrs.

due to it i am unable to change the starting and ending time in probv order.

pls suggest me what to do in this condition


thanx
Nrapendra Singh
(Sr. Tech. Consultant)
Dataman Computer Systems (P) Ltd.
web :www.datamannet.com
mail :nrapendra@datamannet.com

Comments

  • kine
    kine Member Posts: 12,562
    We had some similar problem. We created cusomization, that on the work center we creted some option if the machine center is working in normal "mode" or in "secondary measure unit". If the second option is selected, I modified the process of calculation of the plan and I am not multiplying the time with quantity.

    Look for this code in codeunit 99000774:
      END ELSE
        IF (ProdEndingDate = ProdStartingDate) AND
           (ProdEndingTime > ProdStartingTime)
        THEN
          ProdEndingTime := ProdStartingTime;
    
      LotSize := SendAheadLotSize;
    //xxxxxx>>
      IF Workcenter."Type of Calculation" = Workcenter."Type of Calculation"::SMU THEN
        RemainNeedQty := ProdOrderRoutingLine.RunTimePer
      ELSE
    //xxxxxx<<
        RemainNeedQty :=
          LotSize *
          ProdOrderRoutingLine.RunTimePer;
      RemainNeedQty :=
        ROUND(
          RemainNeedQty *
          CalendarMgt.TimeFactor(ProdOrderRoutingLine."Run Time Unit of Meas. Code") /
          CalendarMgt.TimeFactor(Workcenter."Unit of Measure Code"),
          Workcenter."Calendar Rounding Precision");
      FirstCapNeedinRtngLine := TRUE;
    
    Kamil Sacek
    MVP - Dynamics NAV
    My BLOG
    NAVERTICA a.s.