Date calculations on Production Order Routing lines

jksjks Member Posts: 277
Hi all,

When we refresh any production order, with Calculate Lines and Routing options checked, how navision calculates Starting and Ending date for the Routing Lines?

I also want to know that is there any condition under which routing lines will not be generated eventhough Routing options was checked.?

Thanks for any help.

Comments

  • johnson_alonsojohnson_alonso Member Posts: 690
    When we refresh any production order, with Calculate Lines and Routing options checked, how navision calculates Starting and Ending date for the Routing Lines?
    The system use routing that you have set and certified.
    I also want to know that is there any condition under which routing lines will not be generated eventhough Routing options was checked.?
    if you do not use routing, the system will check based on lead time calculation field that can be set in item card and production lead time field in the production BOM. But there will nothing in the prod. order routing line. if you not use routing. It will be good to use it and your refresh prod. order will successfully result well etiher back or forward.


    Rgds,