Hi guys,
I'm trying to setup a work center to met the following scenario:
I have 3 people with work time:
People A from 7:00 to 15:00 (shift 1)
People B from 15:00 to 23:00 (shift 2)
People C from 23:00 to 7:00 (shift 3).
All of the three people have to operate an extruder Machine which is operable for 24 hours.
How can I set up these people and machine into a work center so I can have a work center with capacity 24 hour?
I already set up a workcenter calendar to have 3 shift with each shift time as I describe above but how can I setup the machine center?
'cause that there is no shift code link to machine center?
Anyone can help me?
BHT
Comments
How come the calendar act like this? I just need to have 3 operator with 8 hour capacity for each and a machine which have 24 hour capacity.
Anyone please help me....?
BHT
Monday 0:00:00 7:00:00 3 Monday 7:00:00 15:00:00 1 Monday 15:00:00 23:00:00 2 Monday 23:00:00 23:59:59 3 Tuesday 0:00:00 7:00:00 3 Tuesday 7:00:00 15:00:00 1 Tuesday 15:00:00 23:00:00 2 Tuesday 23:00:00 23:59:59 3 Wednesday 0:00:00 7:00:00 3 Wednesday 7:00:00 15:00:00 1 Wednesday 15:00:00 23:00:00 2 Wednesday 23:00:00 23:59:59 3 Thursday 0:00:00 7:00:00 3 Thursday 7:00:00 15:00:00 1 Thursday 15:00:00 23:00:00 2 Thursday 23:00:00 23:59:59 3 Friday 0:00:00 7:00:00 3 Friday 7:00:00 15:00:00 1 Friday 15:00:00 23:00:00 2 Friday 23:00:00 23:59:59 3 Saturday 0:00:00 7:00:00 3 Saturday 7:00:00 15:00:00 1 Saturday 15:00:00 23:00:00 2 Saturday 23:00:00 23:59:59 3 Sunday 0:00:00 7:00:00 3 Sunday 7:00:00 15:00:00 1 Sunday 15:00:00 23:00:00 2 Sunday 23:00:00 23:59:59 3
Assign it to the WorkCenter. Calculate the calendar. Assign that Workcenter to the MachineCenter (the calendar is inherited). Calculate the Calendar for the MC.
Now I have a 24 hour capacity : 3*8hrs