With respect to raising purchase orders from the Planning Worksheet, as general rule, is it appropriate to Regenerate the plan each night and only action the suggested order lines where the Order Date <= Today?
Thanks
SH
With respect to raising purchase orders from the Planning Worksheet, as general rule, is it appropriate to Regenerate the plan each night and only action the suggested order lines where the Order Date <= Today?
Thanks
SH
0
Best Answer
-
The regeneration and purchasing circle is very depending on the company using the worksheet. Normally I would advice a couple of days between reordering to group demands and supplies.
5
Answers
-
The regeneration and purchasing circle is very depending on the company using the worksheet. Normally I would advice a couple of days between reordering to group demands and supplies.
5 -
Thank you for your comment. Practically I think it would be every other day. Is the policy to not to place orders early, Order Date <= Today a good idea when the forward production program is subject to change. I am looking to try to minimise the number of action messages.0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions