Production Problem 2 semi finished items made from one block

mnbrookse
Member Posts: 2
In our company we have a make from item which is a block of material which is cut down into 2 different semi finished items. How in Axapta can I handle this process it would seem to myself that one works order can only be used to make one product where clearly here we have one bom item making two separate and distinct products which then go on to make other items. If I call these items being made product A and product B, our scenario is as follows: -
A demand will be placed for product A, this has to be cut from the Block - Product B is a by product of this process which may or may not have a demand at the time of creation.
Have any other companies experienced this problem and how did you resolve it, currently we have a workaround whereby both make too items are held as phantoms on the system and the consumption takes place from the block when these are used to make finished product - this is not at all ideal, and leads to a loss of control in my opinion.
Many thanks in advance of any reply to this issue.
A demand will be placed for product A, this has to be cut from the Block - Product B is a by product of this process which may or may not have a demand at the time of creation.
Have any other companies experienced this problem and how did you resolve it, currently we have a workaround whereby both make too items are held as phantoms on the system and the consumption takes place from the block when these are used to make finished product - this is not at all ideal, and leads to a loss of control in my opinion.
Many thanks in advance of any reply to this issue.
0
Comments
-
This is where you would not use BOM's you would use a formula with by or co-products to enable you to produce multiple outputs from the same works order (called a batch order in this set of AX processes)The art of teaching is clarity and the art of learning is to listen0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions