Work center Resource Addition
Ankasiva
Member Posts: 10
Hi experts.
I have a problem in Routing ](*,) .
WC1 is the work center. per hour cost of WC1 is Rs.1000. 3 Persons are working under this work center.
1. Supervisor cost per hour is Rs.250.
2. Operator cost per hour is Rs.150.
3. Technical person cost per hour is Rs.100.
All are employees of same company,so I have to enter data like above individually in Routing + I need a report like how many hours one employees has worked?
and how can I change cost/Person at Runtime?
I have a problem in Routing ](*,) .
WC1 is the work center. per hour cost of WC1 is Rs.1000. 3 Persons are working under this work center.
1. Supervisor cost per hour is Rs.250.
2. Operator cost per hour is Rs.150.
3. Technical person cost per hour is Rs.100.
All are employees of same company,so I have to enter data like above individually in Routing + I need a report like how many hours one employees has worked?
and how can I change cost/Person at Runtime?
0
Comments
-
Hi Ankasiva
Try using "Unit Cost" field on the output Journal. It is hidden, you need to click show coloumn and get the field on teh front end.
With Regards,
Rajat.0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.7K Microsoft Dynamics NAV
- 18.8K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 333 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 991 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions