I have a problem to define Routing of a FG Item .
Item Code is same , How can define standard Routing for that.
Example:-
Item Code = A
Locations = Loc1,Loc2, Loc3
Loc1 have 90 Machines
Loc2 have 20 Machine
Loc3 Have 100 Machines
All machine have 25 Day Lead Time , During Planning run System Loads machins as per their capacity.
How can creates routing with Considering Location with single Item .
thanks
Jasbir
I have a problem to define Routing of a FG Item .
Item Code is same , How can define standard Routing for that.
Example:-
Item Code = A
Locations = Loc1,Loc2, Loc3
Loc1 have 90 Machines
Loc2 have 20 Machine
Loc3 Have 100 Machines
All machine have 25 Day Lead Time , During Planning run System Loads machins as per their capacity.
How can creates routing with Considering Location with single Item .
thanks
Jasbir
0
Comments
-
Are you producing the same item in different locations ?0
-
Yes, Same Item is produced at Different Location.
But System required Standard Routing Linked at Item Card. When i am going to run Planning(MPS/MRP) Location Wise then system considerd that routing for all Locations.
I want Location Wise Routing.
Regards
Jasbir0 -
We done the follwing functionality to one of our client and using without any problem. ( Client not using the Planning Engine)
you have to create the Seperate table Called Multiple Routing , which contains the fields Item Code, Location code, Routing code . In this table user has to configure the Items, Location and Routing . When user create the Production order , system will check item code and Location code and update that Routing code against that item in the Production order.0 -
But in my problem, Client using Planning.
without customization, can Base handle this problem ?
For Example , in Crounus Demo , Bicycle can be manuf. at many location , how can handle this
Client wants that system auto allocate empty m/c when they are going to run planning.0 -
jasbir wrote:without customization, can Base handle this problem ?
I want to say -No.jasbir wrote:For Example , in Crounus Demo , Bicycle can be manuf. at many location , how can handle this
Client wants that system auto allocate empty m/c when they are going to run planning.
Not possible.jasbir wrote:But in my problem, Client using Planning.
Before modifying it, open the planning engine with the dedugger on: follow the code and try to underestand it. If you do so, you will be able to modify it to feet your needs.0 -
As I undurstood, it will be need to customize,
Thanks for appricating suggestion to me.0
Categories
- All Categories
- 73 General
- 73 Announcements
- 66.6K Microsoft Dynamics NAV
- 18.7K NAV Three Tier
- 38.4K NAV/Navision Classic Client
- 3.6K Navision Attain
- 2.4K Navision Financials
- 116 Navision DOS
- 851 Navision e-Commerce
- 1K NAV Tips & Tricks
- 772 NAV Dutch speaking only
- 617 NAV Courses, Exams & Certification
- 2K Microsoft Dynamics-Other
- 1.5K Dynamics AX
- 320 Dynamics CRM
- 111 Dynamics GP
- 10 Dynamics SL
- 1.5K Other
- 990 SQL General
- 383 SQL Performance
- 34 SQL Tips & Tricks
- 35 Design Patterns (General & Best Practices)
- 1 Architectural Patterns
- 10 Design Patterns
- 5 Implementation Patterns
- 53 3rd Party Products, Services & Events
- 1.6K General
- 1.1K General Chat
- 1.6K Website
- 83 Testing
- 1.2K Download section
- 23 How Tos section
- 252 Feedback
- 12 NAV TechDays 2013 Sessions
- 13 NAV TechDays 2012 Sessions