manual subcontract PO, possible?

B3nz
B3nz Member Posts: 37
Hi all,

is it possible to create subcontract purchase order manually (not using subcontracting worksheet) and assign the PO to the Production Order?

thanks

Comments

  • ssingla
    ssingla Member Posts: 2,973
    Not with standard. You need to customize it.......
    CA Sandeep Singla
    http://ssdynamics.co.in
  • William_Holland
    William_Holland Member Posts: 15
    As far as I know you can enter a PO manually, and update the field Prod.orderno." and "prod.Order line no." in the purchase line with the production order number and the line you create the PO for. That's basically what the carry out message CU does.